Ethiopia’s state railway company has been ordered to pay hundreds of millions of dollars to Turkish contractor Yapı Merkezi, closing a long legal fight over the Awash–Kombolcha–Hara Gebeya railway, a line that was left half-finished when war broke out in the north in 2020.
The London Court of International Arbitration issued its final award on 23 September, and both sides were formally notified on 2 October, according to Yapı Merkezi and trade publications including Railway Gazette International and the International Railway Journal. The company says that, after setting off the Ethiopian Railways Corporation’s (ERC) counterclaim, it is owed a net US$307.6 million, calculated as of 30 June, with simple interest of 9% a year running until the money is paid. Yapı Merkezi told Türkiye Today it had not yet been paid and was pursuing the legal and commercial steps needed to recover the sum.
Two ways of counting
Ethiopian reporting puts the figure lower. Capital Ethiopia, citing information it obtained, reported that the tribunal awarded the contractor $213.7 million in damages, made up of $67.4 million in unpaid amounts, $76.7 million for construction delays and $89.2 million for damage to the company’s assets during the conflict. The tribunal also ordered the repayment of $29.1 million in advance payments. Analysis site Fact.et noted a gap of roughly $94 million between the pre-interest balance and the number the contractor is publishing, which appears to come largely from accumulated interest.
Yapı Merkezi had originally sought more than $1 billion, while the ERC filed a counterclaim of about $400 million, Capital reported. ERC deputy chief executive Seleshi Kassa told The Reporter that Ethiopia had successfully defended itself against more than 70% of the contractor’s claims. Claims against the Ministry of Finance and the Ministry of Transport and Logistics were dismissed, and the contractor was ordered to hand vehicles and machinery from the project over to the ERC. Sources told Capital that neither side intended to appeal.
A line waiting for trains
The 392-kilometre electrified railway, a $1.7 billion project, was meant to link the central Awash area with Kombolcha and Weldiya and carry freight toward the north. Much of the infrastructure had been built, including track on some sections, before work stopped during the 2020–2022 war. The company’s claims centred on war damage, looted equipment and long periods of standby on sites it could not work.
The government has since taken the restoration into its own hands. According to The Reporter, cited by Railway Gazette, ERC crews have repaired around 70 kilometres of track and are preparing for test runs, with the corporation aiming to finish the stretch up to Kombolcha within two years. Repairs are also under way around Dessie.
Neither the ERC nor the Ministry of Finance has said publicly how or when the award will be paid, an open question at a time when hard currency remains tight.